Web Design
Logo05

Landfill Al Multaqaa, Al Amerat, Muscat, Oman

100_000402
IMG_0011

Construction of a new landfill for Muscat, the capital of Oman

Construction of a leachate treatment plant

Construction of the  landfill gas collection pipes and gas collection substations for the  horizontal and vertical gas extraction system

Construction of a receiving area with staff facility building, workshop, garage and weighing facility

Scope of work: Capacity building, site supervision; Resident engineer for Fichtner Muscat

Client:

Muscat Municipality, Sultanate of Oman

Project Management:

Fichtner GmbH & Co. KG, Germany

Design:

ICP GmbH, Germany

Contractor:

STRABAG Oman LLC

Deposit area, total:

466.500 m²

  • 1. Section:

78.000 m²

Deposit volume:

1.275.000 m³

Leachate treatment:

Evaporation pond

Base lining system:

 

  • Landfill:

Asphaltconcrete, 2 liner, wearing course 8 cm,
sealing course 6 cm

  • Evaporation pond:

HDPE liner, 2,5 mm, 2 liner, leakage control

IMG_0023 IMG_0015